Power Cables

Cable Short-Circuit Withstand Calculation: I²t and k²S² Explained

Quick answer: cable short-circuit withstand is checked by confirming that the fault energy allowed by the protective device does not exceed the conductor’s thermal capability. For an adiabatic check, I²t ≤ k²S², or equivalently S ≥ I√t/k.

Why ampacity is not enough

A cable selected for continuous load current and voltage drop can still be damaged during a short circuit. Fault current produces rapid I²R heating, and conductor temperature can rise from its normal operating value to the insulation’s short-circuit limit in a fraction of a second. The cable and protective device therefore have to be checked as a coordinated pair.

The adiabatic equations

For a specified conductor:

Maximum allowable I²t = k²S²

For a known fault current and clearing time:

Minimum S = I√t/k

S is conductor cross-section in mm². I is RMS short-circuit current in amperes. t is clearing time in seconds. k is selected from the governing standard for conductor material, insulation, initial temperature and final permitted temperature.

Worked cable check

Check a 50 mm² copper XLPE conductor for a prospective 18 kA fault cleared in 0.10 seconds. Assume k = 143 for the applicable case.

Required S = 18,000 × √0.10 / 143 = 39.8 mm²

The installed 50 mm² conductor passes this simplified thermal check. The same result can be expressed as energy:

Device energy: I²t = 18,000² × 0.10 = 32.4 × 10⁶ A²s
Cable capability: k²S² = 143² × 50² = 51.1 × 10⁶ A²s

Because 32.4 is less than 51.1, the cable passes the adiabatic comparison. For a current-limiting fuse or breaker, use the manufacturer’s published let-through I²t rather than simply multiplying prospective RMS current by total clearing time.

Which current and time belong in the calculation?

InputUseAvoid
Fault currentProspective current at the cable locationUsing transformer-terminal current everywhere
Clearing timeTotal relay plus breaker or fuse clearing timeUsing only relay operating time
Let-through energyManufacturer I²t for current-limiting devicesAssuming constant prospective current
k factorCorrect material and insulation tableCopying a value from another cable type

Complete verification workflow

  1. Calculate maximum short-circuit current at the start and end of the cable.
  2. Identify the protective device and its total clearing curve or let-through energy.
  3. Select k for the cable conductor and insulation system.
  4. Check phase, neutral and protective conductors for their relevant faults.
  5. Verify peak electrodynamic forces, especially for single-core cables and bus-connected runs.
  6. Check cable terminations, joints, screens and metallic sheaths.
  7. Record assumptions and coordinate them with the protection study.

Cable Short-Circuit FAQ

Does a larger breaker always require a larger cable?

Not automatically. Continuous overload protection and short-circuit energy are separate checks. The device curve, fault level, clearing time, installation method and cable properties all matter.

Why use manufacturer let-through data?

Current-limiting devices reduce both the peak and duration of the fault current. Published I²t provides a more accurate coordination check than assuming the full prospective current flows until clearing.

Does the adiabatic check cover mechanical forces?

No. It is a thermal calculation. Cable cleats, supports, spacing and terminations must also withstand peak short-circuit forces.

Continue with cable derating factors and the updated cable current-carrying capacity guide.

Related Articles